If when setting a sandwich panel to approach the business, as well as make the right calculations, then it is very easy to achieve a result.
Horizontal installation method.
When installing the main material, it will be necessary to carry out additional elements on the base of the building. Mineral wool may also be needed. After these actions are performed, you need to measure the control marks, and then move on to the installation of the first panel.
As the basis for the installation, you need to use the frame. A sandwich panel can be attached to it by using self-tapping screws. Then, in turn, all other panels are installed, but so that they are located down the groove. The same principle of consolidation is carried out as in the first panel.
Then it remains only to fix all the joints between the panels, using mineral wool, to eliminate cracks and joints, apply the mounting foam.
Vertical installation method.
A similar process should also begin with the installation of additional elements on the base. To install the panels vertically, you will definitely need to use special lifts. Each of the panels should be checked for verticality, using a plumb line.
When installing self-tapping screws, you need to start only at the edges of the sandwich panels. You need to start with the upper end. Then he will go down to the runs. After the final stage of consolidation of self -tapping screws, proceed to the application of sealant. After processing the lock of the first panel, start mounting the next.